Executed Project

We are currently Handling Engineering Supervision and Site management for Onitsha – Oba – Nnewi – Ideato – Okigwe 132kV D/C Line 2 X 60MVA, 132/33kV S/S at Oba, 2X60MVA 132/33KV S/S at Ideato and also for the Conversion of low voltage Distribution System (LVDS) to High Volatge System (HVDS) in Kubwa Cluster, Abuja-FCT..
Name of Project Location and Type of Work Performed:

  1. Bid Adjudication, Contract Negotiation and Award for the PHCN Fiscal Year 2010
  2. Consultancy supervision of Alaoji-Umuahia-Okigwe-Ohafia-Mabalano132KV Transmission lines and associated Substations
  3. Consultancy services for the Electrification of GBGIR – AFIA – GBEJI – ZAKI – BIAM in Benue
  4. Adjudication for award of contra-cts for 330/132Kv transmission lines and associated substations.
  5. Consultancy – revaluation of Alaoji/Umuahia DC Trans. Lines Engr. Ltd
  6. Supervision for the Evacuation of power from Katampe 330/132/33kV, DC 2x150/60MVA Substation Abuja.
  7. Provision of commercial power supply @ BTS sites in Enugu Msc. Area – 10 Stations
  8. Provision of commercial power supply @ BTS sites in Sokoto & Kebbi – 9 BTS Stations
  9. Adjudication for award of contra-cts for 330/132Kv transmission lines and associated substations.
  10. Supply, construction and installation of 30No 500/0.415KVA, 33kV Transformers and OH Lines
  11. Provision of street lights at Constantine Street, Abuja.
  12. Management of Electrification of Kuje Area Council
  13. Supervision for the Provision of street lights @ Accra Street, Abuja.
  14. Procurement, Construction and Installation of 300KVA, 11/0.415KV Substation @ Shendam
  15. Supply & installation of 1x7.5MVA, 33/11kV Power Transformer with Associated Circuit Breaker Panel – Jabi Injection Substation
  16. Supervision of 8.2km, 33kV Katampe/Mabushi O/H Lines
  17. Additional 11kv line from jabbi S/S to life Camp, Gwarinpa
  18.  Supervision of Electrification of Gwako village @ voltage level of 33/11kV
  19.  Consultancy supervision of 5km, 33kV Lines and Relocation of 2km, 3kV Berger Junction Lines feeder
  20. Provision of feeder 33kv lines and installation of 1x !% MVA Power Transformer and reticulation of 600 Houses 11/415Kv at Gwagwalada
  21. Government Grammar School ICT Centre
  22. Construction of 132/33Kv switch yard for NEPA at Azare
  23. Consultancy Supervision of Electrification of Garam village in FCT

 